Project Description

  • Kwest Group performed full-depth removal of over 75,000 square yards of asphalt and concrete pavements
  • Pavement sections ranged from 6″ to 16″
  • Placed nearly 30,000 tons of aggregate subbase material
  • Work required close coordination with Airfield Operations Personnel
  • Installed 12,400 linear feet of 18" waterline which connected multiple well field pumping stations servicing Holloman Air Force Base
  • Project included excavation and installation of waterline through sensitive desert ecosystem as well as adjacent to existing public roadway