City Lakes Substation Sitework


Location: Mt. Pleasant, Texas

 

Project Description

  • New substation project required 6,100 cubic yards of cut to fill and exported excess soil to mound
  • Installation of 1,105 cubic yards of flex base material for roads and pad
  • Concrete paved entrances with 272 feet of 6' curb
  • Placed 230 feet of 18” reinforced concrete pipe, 3 catch basins and cast-in-place headwall with wing walls
  • Close coordination with the City of Mt. Pleasant to remove 494 feet of 16" water line and install 579 feet of relocated 16” water line
  • Rip rap was placed on station slopes
  • Installed 322 square yards of concrete paved channel